Cookies

We use essential cookies to make our site work. We'd also like to set analytics cookies that help us make improvements by measuring how you use the site. These will be set only if you accept.

For more detailed information about the cookies we use, see our cookies page.

Essential Cookies

Essential cookies enable core functionality such as security, network management, and accessibility. For example, the selections you make here about which cookies to accept are stored in a cookie.

You may disable these by changing your browser settings, but this may affect how the website functions.

Analytics Cookies

We'd like to set Google Analytics cookies to help us improve our website by collecting and reporting information on how you use it. The cookies collect information in a way that does not directly identify you.

Third Party Cookies

Third party cookies are ones planted by other websites while using this site. This may occur (for example) where a Twitter or Facebook feed is embedded with a page. Selecting to turn these off will hide such content.

Skip to main content

SGN - Gas Network Upgrades - Shottendane Road Margate

By Elizabeth J. Carr BA(Hons) MBA - Parish Clerk & RFO Manston Parish Council

Monday, 3 August 2026

ABOUT THE AUTHOR

Manston Parish Council Contributor

VIEW ALL ARTICLES BY THIS AUTHOR

Update - Friday 31 July

Our engineers are making steady progress upgrading our gas network on all approaches to the Coffin Corner junction:

  • We've inserted nearly 200m of new pipe along Nash Road and 118m has been installed on Shottendane Road
  • Approximately 100m of old main has been decommissioned so far
  • 15 supply pipes serving nearby properties have been upgraded to date

Next week, we plan to install around 100m of new pipe along Manston Road.

That's before we begin connections across all five roads approaching the junction. This part of our work will be complex due to the number of other utilities located underground.

To carry this out safely, we'll now be using specialist equipment mounted on HGVs. Despite the engineering challenges, we remain on track to complete our project on schedule.

We're working closely with other utilities at this junction. Coordinating activities now will help reduce future disruption at this busy location.

Following feedback from road users, we've adjusted signage to make the traffic management measures around the site clearer.

Thank you for your ongoing patience and understanding while this essential work is carried out. Further updates will be posted here https://www.sgn.co.uk/our-gas-works/major-planned-projects/margate-shottendane-road

Kind Regards

Helen Peile, Stakeholder and Community Manager

E: [email protected]

SGN, St Lawrence House, Station Approach, Horley RH6 9HJ

Connect with us at www.sgn.co.uk, on LinkedIn, on Facebook, on Instagram and on X.

Smell gas? Call 0800 111 999

Find out how to protect your home from carbon monoxide